- We had a great summer to get out of the ground at Richmond Road. Construction activities have moved better than expected.
- Deep foundations or Caisson are 100% complete.
- Installation of footings are 85% complete.
- Interior demolition of the old Dillards is 98% complete.
- Demolition of canopy along west elevation of old Dillards is underway, with plans to remove steel structure starting tomorrow.
- EOP Architects completed the Contract Drawings and were submitted to LFUCG on September 13 for Final Permitting.
- Messer Construction sent out the Contract Drawings for bidding September 15 to selected subcontractors with bids due on October 6th. We have 22 different work catagories we are bidding.
- Structural Steel for the new Auditorium will begin on October 3 with completion of the steel frame to be complete by November 10.